Skanska Market Trends Report upacks causes of cost escalation, extended lead times in construction
Skanska, a global construction and project development firm, has released its Fall 2026 Construction Market Trends Report, examining the forces shaping the U.S. construction market as the industry approaches the end of the year. The report finds that rising demand from data center and technology-related development, shifting tariff policies and ongoing supply chain constraints are contributing to significant cost escalation and extended lead times across key construction materials and equipment.
While construction activity remains uneven across sectors, elevated demand for structural steel, electrical gear, generators and other critical materials continues to create challenges for project owners and contractors navigating budgets and schedules.
“As we look toward the end of 2026 and into the year ahead, the construction industry continues to face a complex combination of demand-driven pressures and supply chain constraints,” said Steve Stouthamer, executive vice president of project planning at Skanska USA Building. “The unprecedented pace of data center and advanced technology development is putting significant pressure on materials, equipment and labor availability, while evolving tariff policies and geopolitical conditions are adding another layer of uncertainty. Owners and contractors need to be increasingly proactive in their planning, procurement and evaluation of alternative materials and delivery strategies to help mitigate cost and schedule risks.”
The report highlights a construction market experiencing diverging conditions across sectors and geographies. While nonresidential construction activity continues to benefit from investment in data centers, manufacturing and institutional projects, residential construction and certain commercial markets remain more subdued. Construction costs are also showing renewed upward momentum, with the ENR Materials Index increasing 9.3% over the 12 months ending in November 2026. Meanwhile, Skanska's blended Composite Cost Index increased 6.1% over the same period, reflecting continued escalation in mechanical, electrical and plumbing (MEP) trades alongside broader construction cost pressures.
With experience across diverse sectors nationwide and globally, Skanska brings a unique perspective on emerging industry trends, with key report highlights including:
- Construction costs are accelerating, driven by materials and specialized trade pricing:
—The ENR Materials Index increased 9.3% over the 12 months ending in November 2026, compared to a 2% increase during the same period the prior year.
—Skanska's blended Composite Cost Index increased 6.1%, with MEP trade pricing rising approximately 8.2% annually.
—The ENR Building Cost Index increased 4.6%, while the Construction Cost Index rose 2.8 percent over the same period.
- Structural steel costs and lead times are rising significantly amid unprecedented demand:
—Cold-rolled coil and standard plate costs increased 48.9% and 46.4%, respectively, over the 12 months ending in October 2026.
—Structural steel demand remains elevated due to data center and manufacturing development, with lead times reaching 60 weeks or more in some markets.
—New tariffs on Canadian fabricated steel are adding further cost pressure and uncertainty to procurement.
- Extended lead times for critical equipment continue to challenge project schedules:
—Generator availability for large-scale data centers now commonly exceeds 100 weeks, while medium- and low-voltage switchgear lead times exceed 52 weeks.
—Liquid-filled transformer lead times range from 60–85 weeks, while HVAC equipment lead times can reach 52 weeks.
—Electrical gear prices are expected to increase more than 10% in 2026, with HVAC equipment pricing expected to rise 8%–10%.
- Tariffs, fuel costs and geopolitical conditions are adding pressure across construction supply chains:
—Copper wire prices have increased more than 25% in some markets since the beginning of 2026, while roofing membrane and polyiso insulation prices have risen 10–15 percent and 8–12 percent, respectively.
—Ongoing U.S.-Canada trade tensions and evolving tariff policies are creating additional uncertainty for steel, lumber and other construction materials.
—Higher diesel prices are contributing to increased transportation, logistics and material delivery costs.
- Early planning and flexible project delivery strategies are increasingly important to managing market volatility:
—Owners and contractors should account for extended lead times across structural steel, generators and electrical equipment when establishing project schedules.
—Evaluating alternative materials and structural systems earlier in the design process can help mitigate supply constraints and cost exposure.
—Skanska's Strategic Supply Chain Team monitors manufacturer capacity, material pricing and supply chain conditions across 68 material and equipment categories to help project teams anticipate potential impacts.